Replacement of windows on the entire 1st house

Fasaden og et stort vindu på østsiden av Musikkhøgskolen.

From 5 February to the end of August 2024, Statsbygg will replace the windows in the entire 1st building.

Progress plan

This happens in a given order of approx. 10 windows per bolk. A bolk takes 14 days.

The window is taken out - the frame is treated - and the window gets new glass - the window is put in and must then be in top condition.

The rooms are not very accessible/user-friendly during these 14 days.

Progress plan - we will probably adjust somewhat along the way: